Tuesday, August 31, 2010

Mondays Concrete Has Been Postponed

Ugh!!! So Mondays concrete pour has been postponed until Thursday, but it is supposed to rain on Thursday, so I cant see them getting it done until next week. They had prior comitments, and didn't have any finishers to do our pour.

But we didn't know that, until we got home real late Sunday Evening, so Mary and Kyle busted their butts trying to get it all done for an early Monday pour...

Sunday Mary, Kyle, Jennifer and I got the Sono-Tubes dug, placed, plumbed and reburied. These are for our porch posts, there are 12 of them, they need to be securely set below the frost line.

They are 36 - 44 inches deep. Depending on how difficult the digging was at that depth.


We remembered to put in the pipes for the Fireplace Air Intakes, they went in just perfect.


And then we re-leveled everything and used the tamper to get it all smooth again.